Timeline

End of April 2008
Set financial target - completed

End of April 2008
Finalize budget - completed

Mid May 2008
Cabinet launch meeting - completed

August 2008
Building purchase - completed

February 2009
Design concept approved - completed

March 2009
Prepare construction documents - completed

April 2009
Demolition and renovations begin - completed

May - June 2009
Public launch of project - completed

August 2009
Move from 4050 St-Urbain to 111 Duluth West - completed

May - December 2010
Occupation date of 111 Roy

 

 